INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Ballpark cost ratio

Ballpark cost ratio

Ballpark cost ratio

(OP)
Hello,

I was wondering if there are electric utility industry ballpark figures for cost of engineering design and bid spec versus build cost for substations.  For example, as an estimate, if a substation were to cost $2 million, the design and bid spec prep would be roughly $200,000

RE: Ballpark cost ratio

I think it depends too much on the particulars of the project to say. Could be 7% to 15% or more depending on complexity.

RE: Ballpark cost ratio

For green field site, your 10% is probably in the "ballpark", maybe a little on the low side.  I think alehman's range is reasonable.  


 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources