INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Driven Piles...Energy per Blow and Set

Driven Piles...Energy per Blow and Set

Driven Piles...Energy per Blow and Set

(OP)
Hi guys,

I haven't dealt too much with the design of precast driven piles but today I was given the job of specifying the hammer mass, drop height and set of a driven pile.

I spoke to a piling contractor over the phone to try and determine a generic hammer mass and drop height, only to be told it depends on a number of factors and the contractor needs to know more specifics of the job before they can give an answer.

Basically, the mass of my pile is 12 tonne (26,400lbs) and I was thinking of using a 12 tonne drop hammer. If I drop it from a height of 900mm (3ft) and using a efficency factor of 0.95, this gives me a energy per blow (10.3 tonne meters). My question is:

How do I know what energy input per blow is required to drive the pile? I am driving through silty clayed sand down to weathered sandstone (rock).

I am also required to specify a pile set which is given by a Hiley formula:

S=9800x(Mm+e^2*(Mf+Mp))/(Mm+Mf+Mp)*E/R-0.5*C

where
 
Mm=Hammer mass
Mf=Mass of Pile Helmet
Mp=Mass of Pile
e=co-efficient of restitution, 0.25 to 0.4
E=Energy input per blow (calculated above)
R=Minimum ultimate capacity of pile (3200kN)
C=Combined temporary compression of the helmet cushions, pile and adjacent ground in millimeters.




 

RE: Driven Piles...Energy per Blow and Set

i'd advise that you consult a local or the project geotech

RE: Driven Piles...Energy per Blow and Set

asixth - Msucog is right. Also, on many projects selection of the hammer is left to the Contractor (with approval by the Engineer). This helps to increase bidding completion since various Contractors have (cost-effective) access to different equipment

However, if you have to do this project yourself, a good place to start is with the US Army Corps of Engineers publication, "Pile Driving Equipment". A free download at this link:
http://www.wbdg.org/ccb/DOD/UFC/ufc_3_220_02.pdf

Just of information, IMHO, the worst choice would be a drop hammer (which you mentioned) - they are slow, and totally dependent of crane operator skill.

I also have information on various pages of my website; all of it is old, and most of it is oriented towards timber piling.  For background info you may want to look, starting here:
http://www.slideruleera.net/AWPI-Page.html

www.SlideRuleEra.net idea

www.VacuumTubeEra.net r2d2

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources