INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

teamstatus

teamstatus

teamstatus

(OP)
Suppose manager of a project send a message of TeamStatus for a fixed duration activity, and the resource replies he has completed a part of work. When manager updates project, duration of activity doubles. Why?

Example:  
activity with duration 8 days
manager send message of teamstatus
reply is: work completed = 7 days, work remaining = 1 day
after updating project, duration=16, while it would be more logical a duration of 9 days.

Thanks for any help          Pietro

RE: teamstatus

I've seen durations change because I changed the Units % (found under Resource tab when bring up Task Information).  While sometimes I purposely do this to reflect reality (i.e., person working 2 projects), perhaps a data entry mistake was made with the wrong tab being displayed?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources