INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Create calendar for 9/80 work schedule

Create calendar for 9/80 work schedule

Create calendar for 9/80 work schedule

(OP)
Hey all
I am trying to figure out how to make a calendar for 9/80 work schedule. I am using MS Project 2007 standard edition.
The work week would be as such - week 1 Monday thru Thursdays 9 hrs/day with Friday at 8 hrs. Week 2 Monday thru Thursday 9hrs/day with that Friday off. Just need for figure how to get Fridays set. Just started using 2007 for just a couple of weeks. Calendar setup is somewhat different from 2003. Just bought a Bible(Elaine Marmel)but still scanning it. Thanks in advance for any help.
Bob

RE: Create calendar for 9/80 work schedule

With the new calendar set up you will need to do each Friday individually - because you are doing every other Friday there are not global set up options.  there are only global set ups for time off - not time on.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources