×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Helical Pile resistance

Helical Pile resistance

Helical Pile resistance

(OP)
I am designing a foundation for a large arch building. The engineer who is designing the superstructure gave me reactions at the pedstals where the arches fall.

The horizontal loads are about 80k and in order to resist this horizontal load we are using battered helical piles. The soil is good, so the plan is to resist the vertical loads using a spread footing with the piles attached to resist the horizontal.

Is this possible? I need a better good batter to resist the horizontal load, and I am assuming the vetical component of the piles is resisting some of the vertical load and the rest is resisted by the soil bearing.

The owner does not want to use a truly pile supported foundation because of cost. The geotech also says that we should not count on passive pressure, but the soil is good enough for shallow foundations.

Does anyone have a good idea about how to model this?

RE: Helical Pile resistance

Is it possible to provide a tension tie across the building (buried in the ground) to resist the thrust imposed by the arches?

RE: Helical Pile resistance

'I need a better good batter to resist the horizontal load, and I am assuming the vetical component of the piles is resisting some of the vertical load and the rest is resisted by the soil bearing. '

I would be carefull of this approach, as I think you will have a deflection compatability problem. The piles will be very stiff and intially attract most (if not all) of the vertical column load, where as little of the load will be taken by soil bearing as it is usually assumed that some  settlement is required to develop the full bearing capacity of the soil.

I agree with SteelPE that, if possible, a tension tie might be a good solution here.

JMHO

RE: Helical Pile resistance

(OP)
That is the other option, but we are trying to get pricing for both. The span is 205', so the tension tie has to go a long way, and the short sides of the building will be a problem as well because we would have to go 320' to go from short side to short side.

RE: Helical Pile resistance

I usually see "hairpins" used for this.  A piece (or pieces) of rebar bent in a "V" around a connectoin point at the base of the arch, with both legs extending into the interior slab (assuming there is one). A mass of concrete could be used as a dead-man under the slab if you need more resistance.

I dont know why helical piles would not work also.  I agree that they should only be there for horiz. thrust, not "some of the vertical load".  Load attracts to the stiffest element.  

Also, getting a steep enough batter to keep the upper stem of the helical pile from wanting to "bend and pull laterally through the upper layers of soil) might be practically difficult.

RE: Helical Pile resistance

Key,

I have seen the hairpin detail you are talking about.  I have always been told that a hairpin would be used for small loads (<20k) anything greater and you would need to use a tie.  I have also been told that they are very unreliable as they are rarely installed correctly.  I try to avoid them whenever possible.

I'm not sure what others think but this is what I have been told.
 

RE: Helical Pile resistance

What is the maximum batter you can get out of the piles?  Can you not angle the piles to represent the direction of the reactions.  That way your piles are working axially only.

Surely, though, the best bet is to use the tie under ground and then just to support the building with conventional footings.  The fact that the ties go for a long way surely can't equate to the costs of piling?  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources