schedule 5 pipe repair
schedule 5 pipe repair
(OP)
Is anyone familiar with the old Poz-Lok system using sch 5 thinwall pipe? We need to make repairs to pipe in this system and fittings are no longer available. Any ideas of how to connect this sch 5 to regular sch 40 or sch 10? What would be ul approved method-- possible slip fittings? Any help is appreciated.





RE: schedule 5 pipe repair
How will a different schedule of pipe affect the calculations? It may be a concern if you are replacing large sections.
Travis Mack
MFP Design, LLC
RE: schedule 5 pipe repair
RE: schedule 5 pipe repair
You'd have to rent a tool and purchase some fittings but it's sch. 5.
http://www.victaulic.com/content/pressfit.htm