INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

HEC-RAS Dam Break

HEC-RAS Dam Break

HEC-RAS Dam Break

(OP)
Hi All,

It's my first time working with unsteady flow. I'm using a FEMA RAS model in order to determine the hazard classification of an existing dam.
The reach from the dam to the mouth is 2 miles long and includes numerous crossings.
Hydrographs at the dam (before breach) developed with WinTR-20 are available.
I already looked in the HEC-RAS User's Manual Chapter 16, Chapter 8 Performing an Unstedy Flow Analysis and Example 17 Unsteady Flow Application. I feel that I need extra help and/or access to additional literature describing a step by step procedure using HEC-RAS Dam Break.
I'm not sure exactely what boundary conditions (U/S, D/S and initial) to use. Could be the existing hydrograph before the breach the U/S boundary condition? D/S and initial? What are they exactly in the unsteady flow?
Also I'm having problems finding the RAS window for the control of the dam gate in the unsteady flow data.
I'm looking to get water depths and velocities and using some available charts to determine the hazard classification.
As you can see, I'm strugggling with this very interesting exercise. Please help.       

RE: HEC-RAS Dam Break

The noted "Francesca" will tell you to spend some quality time with the Hydraulic Refernce Manual.

RE: HEC-RAS Dam Break

I may or may not have typed that very response in last night, only to change my mind about posting it, only because I wasn't sure if HEC-RAS was even the right application for a dam break analysis. Certainly in my hydrology class we used WMS, but then WMS is just a very nice GIS wrapper for a lot of HEC programs anyway.  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources