Storage Battery Commissioning
Storage Battery Commissioning
(OP)
I understand that when a new flooded storage battery is installed and assuming they are dry charged. An electrolyte filling process will be undertaken as per manufacturer recommnedations. After the correct electrolyte level has been filled in, an initial "freshening charge" (constant potential method) or initial equalization voltage will be applied for a specific period of time as specified by the battery manufacturer. After the battery is fully charged, we will conduct a discharge test using a load bank to veiryf its discharge rate.
If we have a new battery charger designed and size for this new battery system, can we use initially test and commission it and use it to provide the initial charging for the new batteries?
If we have a new battery charger designed and size for this new battery system, can we use initially test and commission it and use it to provide the initial charging for the new batteries?






RE: Storage Battery Commissioning
RE: Storage Battery Commissioning
Keith Cress
kcress - http://www.flaminsystems.com
RE: Storage Battery Commissioning
For batter Cx, have a look at IEEE 450.
RE: Storage Battery Commissioning
The battery manufacturer will almost certainly have a specific commissioning procedure which must be followed to maintain the warranty. It is a good idea to use a chart recorder or similar to provide evidence that the procedure was followed accurately in the even of a claim.
----------------------------------
If we learn from our mistakes I'm getting a great education!
RE: Storage Battery Commissioning
I will check the new battery charger and battery specs and see the battery initial charging requirements and check whether this value is within the new battery charger equalization voltage setting range.
If yes, then I can commission first the battery charger then the battery right?
Is the initial charging similar to boost charging? How does this differ to the equalization charging?
Thank you.