×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pressure Testing

Pressure Testing

Pressure Testing

(OP)
Possibly a very stupid question, but I am looling for some opinions.

A section of pipework is due to be pressure tested according to ASME B31.1, and there are 2 flanged valves not yet installed as they have not been delivered.

How would one define the limits of the pressure test for the above example. Is it of the piping only, or should it include all equipment which would be normally installed (other than those which may be damaged by the pressure test)? What section of B31.1 defines the scope?

If 2 dummy/spacers were installed for the test would this suffice?

Should the contractor wait for the valves to be installed before carrying out the test?

Thanks in advance for any opinions offered.

RE: Pressure Testing

Bottle;
You have two options that I see;

1). Blank off the existing piping, perform a pressure test and after delivery of the valve bodies weld them in and perform a volumetric examination (RT or UT) of the connecting welds only.

2) Wait until the valve bodies are delivered and perform a pressure test on the completed assembly.

RE: Pressure Testing

You don't mention material type.  If any PWHT is required, you'd have to wait until the valves are installed as per 137.1.5.

It can be done as metengr mentioned.  However, it is highly preferred to be done after the valves are installed.  I just asked one of our senior QC guys, and he mentioned that the installation of the valves after testing would typically have to have both client and engineering approval in order to take place.   

RE: Pressure Testing

(OP)
Thanks for the responses.

The piping is GRP, however we have agreed that for pressure testing that we will go along with B31.1. So no PWHT required.

 

RE: Pressure Testing

Why would PWHT be an issue?  He said the valves are flanged.

Edward L. Klein
Pipe Stress Engineer
Houston, Texas

"All the world is a Spring"

All opinions expressed here are my own and not my company's.

RE: Pressure Testing

Test the flanged piping.  When the valves come, open them, flange them together and test them, then do your final assembly.  No different than partial testing of various pieces of piping that are connected by flanges only, or say the piping which is connected to a nozzle on a vessel (both tested separately prior to installation).  Piping connnected by welding of course needs to be tested after the last weld is done.  

The flanged joints between the valves and the piping can be tested for leakage in service, with the owners' permission of course.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources