INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Precast Wall Panel - Keyway Footing

Precast Wall Panel - Keyway Footing

Precast Wall Panel - Keyway Footing

(OP)
One of the precast wall suppliers I work with has indicated that the typical grouted keyway footing detail is no longer considered acceptable.  I have searched for documentation to confirm this with no luck.

Has anyone else encountered this situation?

Thanks!

RE: Precast Wall Panel - Keyway Footing

The keyway design which has a 2"x4" pultrusion into the other shape is worthless.  Imagine a crack which can go anywhere.  The two re-entrant corners will define a stress concentration from which a crack can traverse, negating any shear contribution from the pultruding concrete.  Steel crossing the plane of the construction joint and a slightly roughened surface with the concrete laitence removed is the gold standard for transfering stresses across the joint.  If water stop is added then the joint is the best for water containment.

RE: Precast Wall Panel - Keyway Footing

I don't think that is the type keyway the OP was talking about.  He didn't get any response until now, so I guess no one had any advice.  I would read his question as applying to the type footing which is cast with a big slot for precast panels, then grouted after erection.  But perhaps the OP can clarify and try again.

RE: Precast Wall Panel - Keyway Footing

(OP)
hokie66 is correct.  The detail I am referring to utilizes a 3" deep keyway cast into the top of the continuous wall footing.  The width of the keyway is typically the thickness of the precast wall panel plus 3".  The panel is set on a ship pack in the keyway and grouted into place.

Hopefully, this clarifies the situation I tried to explain in my first post.

Thanks!  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources