INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

OWSJ, bottom chord connection

OWSJ, bottom chord connection

OWSJ, bottom chord connection

(OP)
Hello all,

I was inspecting a couple of floor joists today when I noticed that the bottom chord of a couple of joist had a plate welded to it with 2 holes (presumably to connect the bottom chord) but the plate/end of the bottom chord was so far off from the connection point that the contractor simply did not bother and left it alone. The problem is that the drawings that we have at present are not enough for me to determine whether or not the bottom chord should be connected. The floors joists in question span into a much stronger truss of equal depth, so the bottom chord of the joist would span into the bottom chord of the stronger truss. Is this typical? I thought bottom chords are connected at column locations only. I would hate to specify that the bottom chord is to be connected when the original designer did not intend them that way. I hope my question is clear.

RE: OWSJ, bottom chord connection

If the diagonal terminates at the support point of the top chord you probably don't need bottom chord connection.
If it terminates at the end of the bottom chord you definitely need the bottom chord to be supported.

RE: OWSJ, bottom chord connection

Typically the bottom chords of OWSJ are not rigidly attached to anything unless required by the EOR.  If the bottom chord is rigidly attached then the engineer must supply the joist manufacturer with the axial load induced in the bottom chord so they can design their joists properly.  This axial load must be indicated on the structural drawings.

You may need to contact the EOR to clarify.
 

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources