equipment and labor cost escalation
equipment and labor cost escalation
(OP)
Need suggestions on equipment and installation escalation for 1/2006 to 6/2008 , are there any public forums to get data ?
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
equipment and labor cost escalation
|
RE: equipment and labor cost escalation
Materials costs have been extremely variable over the past few years. And labour cost is entirely regional.
RE: equipment and labor cost escalation
CEPCI for Jan 2007 preliminary was 509.8
CEPCI for Jan 2008 preliminary was 530.7
That is the latest I have.
This is the index from the back of Chemical Engineering magazine to which moltenmetal refers.
HAZOP at www.curryhydrocarbons.ca
RE: equipment and labor cost escalation
RE: equipment and labor cost escalation
CEPCI for Jan 2007 pvf 724.9, labor 310.8
CEPCI for Jan 2008 pvf 743.8(both prelim), labor 314.0
HAZOP at www.curryhydrocarbons.ca
RE: equipment and labor cost escalation
RE: equipment and labor cost escalation
Mark Hutton
RE: equipment and labor cost escalation
For the past several years, our vendors have been quoting 7 day validities for anything with a significant materials content.
So you can use the CPI crap on the back of Chem Eng magazine if you want, but take it with an appropriate measure of salt. I suggest that you'll be looking in the garden shed rather than the cutlery drawer for the correct measure...