INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

sediment control for dredging project

sediment control for dredging project

sediment control for dredging project

(OP)
I am working on a relatively small, aprozimately 2 acre pond, dredging project in upstate New York; and I am trying to find a way to keep sediment from flowing out of the outlet weir. I've been looking at turbidity curtains but I don't think I can use them across a flowing watercoarse. I know they could use the turbidity curtain if they broke the work up into a couple phases, probably at least 4, but I think that seems a bit excessive for the job.

Does anyone have any ideas how I can keep the dirty water in the pond and allow the clean water to continue flowing out.

Thanks

RE: sediment control for dredging project

Use your turbidity curtains on either side of a channel through the pond to the weir.  Work outside of the channel will have a chance to settle or filter prior to leaving pond.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources