INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Produced water degasser

Produced water degasser

Produced water degasser

(OP)
I am attempting to design a produced water degasser.  The water will be first separated in first / second stage 3 phase separators and then pumped to a break tank.  After this the water is pumped through hydrocyclones to reduce the hydrocarbons to 30-40ppm.  

The produced water degasser will receive approx 45,000bbl/d of water. What I am really interested in is a required liquid residence time for the liquid in order to size the degasser.  Would this usually be a vertical vessel?

Cheers

 

RE: Produced water degasser

For degassing you should use a horz. vesseæ in order to minimize the travel distance for bubbels and maximize contact area.

You company engineering standard may state something about residense time?

If not GPSA/API has some guidelines.

Best regards

Morten

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources