INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Concrete Placement in Tidal Zone

Concrete Placement in Tidal Zone

Concrete Placement in Tidal Zone

(OP)
I have a concrete pier project where the pile caps will have to be poured within the tidal zone of the Chesapeake Bay (Brackish Water). It is possible that the new concrete could be submerged after placement due to tides. What measures would be recommended to protect the concrete during curing of the bents?

Richard Beard, PE
Century Engineering, Inc
www.centuryeng.com

RE: Concrete Placement in Tidal Zone

None, the forms left in place for seven days and cure compound sprayed elsewhere is sufficient.  (If forms are removed early, then respray the exposed surface with pigmented cure compound.)

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources