INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Seismic Analysis of Elevated Silo

Seismic Analysis of Elevated Silo

Seismic Analysis of Elevated Silo

(OP)
I'm working on the analysis of an elevated sand storage silo.  The silo is 65 feet high and 19 feet in diameter.  The base of the round section and the top of the cone base is at elevation 29 feet.  The bottom of the cone is at elevation 16 feet so truck can pass underneath.  The frames are crossed braced only in the upper cone section.

I'm looking at section 15.7.10 of ASCE 7-05.  I'm wondering how to calculate the natural period of the structure.  I'm not designing the silo frame, just the foundation.  The NEHRP section 14.4.7.9.5.2 state AWWA D100 has a method of determining the natural frequency for elevated tanks.  I don't have a copy of AWWA D100.  Can some who has a copy tell me if the standard would have sufficient information in it to help me determine the natural period for the structure from this limited information?

Are there other traditional methods for calculating the natural period of the silo structure?

Thanks for your help.

 

RE: Seismic Analysis of Elevated Silo

I think to figure out the natural frequency or period you will need to do structural analysis on the structure to figure out the stiffness at each bay and the mass.  I would just tell whoever design the frame to figure it out.  I dont have my structural dynamic book with me, Ill look at it when Im home.  It has been a while.

Never, but never question engineer's judgement

RE: Seismic Analysis of Elevated Silo

I agree with COEngineer, the silo manufacturer had to figure this out for design of his tank framing, it should be no big deal for them to give you ALL the loads imparted to the foundation.

RE: Seismic Analysis of Elevated Silo

AWWA D100 still requires some analysis of the deflection characteristics of the tank.  The loads on the foundation should come from the silo designer.

RE: Seismic Analysis of Elevated Silo

(OP)
The silo manufuacturer says he never has had to do a seismic design before.  I guess he never sold it in seismic country.  He forwarded the framing drawings to me and told me if I wanted it to do it myself.  Unfortunately I have no control over the silo manufacturer.  My client bought the silos and is tight with money so my complaining won't go far.

 

RE: Seismic Analysis of Elevated Silo

Sounds like a sticky situation.  There are some issues with liability and ethics here, although that's not the question at hand.  Are you trying to design foundations for it, or just check the overall adequacy or what?

A couple of approaches come to mind.  In the ASCE 7 equations, they are generally of the form V = "this but need not be greater than this".  That is, there's an upper bound on the seismic loading regardless of the period.  If the seismic accelerations are fairly low, you may be able to work with that upper bound and design your work without getting too overly-conservative.

If you are only designing foundations, the design loads on the foundation would not need to exceed the ultimate strength of the structure.  If you can calculate the maximum shear and axial load the columns can generate, that may give you a means of design.

Since the lower part of the structure is not cross-braced, you could treat the entire upper structure as a rigid body, calculate deflection in the unbraced legs only, and derive a period without too much trouble.  The actual period should be somewhat longer, and depending on the period, this may be a conservative estimate.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources