INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

MS project dates

MS project dates

MS project dates

(OP)
Hello I have a problem understanding how MS project calculates the duration from the start and finish dates.
for example i have a start date Wed 23/04 and a finish date Wed 30/4 which gives according to ms project 5 days..
To me it should 6 days.. what am I missing??

RE: MS project dates

You are missing several steps:

Is this an assignment?  What is the task type?  When is the predessor task completing? If there is no assignment, look at the project calendar availability of working time, the options for calendar time and the ending time of the predessor task.  That will let you know why it is taking longer than you expect.

Good luck
E. Lehnert, PMP - Certified MS Project instructor
www.lehnertcs.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources