I have a certifcate for ASME VIII, 1 Shop manufacturing. I would like to do also some field work. What do I have to do? Change the manual and have a new joint review?
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS Come Join Us!Are you an
Engineering professional? Join Eng-Tips Forums!
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail. Posting GuidelinesJobs |
Change ASME VIII shop to field
|
RE: Change ASME VIII shop to field
RE: Change ASME VIII shop to field
I found the attachment here at the ASME Committee Website:
ht
This is the ASME Conformity Assesment Procedure for conduct regarding ASME SURVEYS, REVIEWS, AUDITS, INVESTIGATIONS AND INTERVIEWS.
In the attachment, go to page 21 to read the policy for a "scope change" or "scope expansion".
There are three kinds of people in this world; those who can Google and those who can't.
RE: Change ASME VIII shop to field
RE: Change ASME VIII shop to field
So another audit seems to be necessary. I will have to wait two years.
RE: Change ASME VIII shop to field
Obviously, the cleanest way is to amend your certificates for both Shop and Field in the Scope of your Quality Manual and add any other controlling features specific to field work when renewing your current Certificate during the the Joint Review audit process.
RE: Change ASME VIII shop to field
Regarding my signature line, I think you underestimate the powere of Google. But everyone has their preferences.
RE: Change ASME VIII shop to field
I found the following below using Google: It may help you decide how to approach your AIA....