2 drainage areas w/culvert
|
RE: 2 drainage areas w/culvert
Pond A is formed by the roadway impoundment, with a culvert outlet, and perhaps an overflow weir in case the road overtops. The pond outflow is routed to reach B.
Reach B represents the flow through subarea B. This may be a channel or overland flow. For details see www.hydrocad.net/overland.htm
Sucat B drains into reach B -or- into another summation point downstream, depending on where the flows combine.
Peter Smart
HydroCAD Software
www.hydrocad.net