INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

column ties - when to alternate ?

column ties - when to alternate ?

column ties - when to alternate ?

(OP)
By definition cross-ties must alternate ends when placed.  Ref ACI-318.

In columns that have ties with seismic hooks, is there a requirement for these ties to be alternated?  Or is the alternating of ties engineer’s preference and if so this preference is based on what criteria?

RE: column ties - when to alternate ?

See section 21.4.4.1.  Crossties (135 degree hook on one end and 90 degree hook on the other end) must be alternated.  But hoops with all 135 degree hooks are not required to be alternated.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.