Custom View
Custom View
(OP)
Hey everyone,
Hope you guys can help me with this. I'm looking to create two views. One view is to show me the following:
Resource name Week 1 Week 2 week 3
Day 1,2,3 Day 1,2,3 etc.
-Resource #1 ---Project (P) name 1--- ---P 2--- etc-
-Resource #2 ------P Name 1---- P Name 2 -------
-Resource #3
-Resource #4
View #2
Project Name Week 1 Week 2 Week 3
-task 1 ------Resource Name----
-task 2
Any help would be greatly appreciated. My job is dependent on this.
Thanks in advance
Hope you guys can help me with this. I'm looking to create two views. One view is to show me the following:
Resource name Week 1 Week 2 week 3
Day 1,2,3 Day 1,2,3 etc.
-Resource #1 ---Project (P) name 1--- ---P 2--- etc-
-Resource #2 ------P Name 1---- P Name 2 -------
-Resource #3
-Resource #4
View #2
Project Name Week 1 Week 2 Week 3
-task 1 ------Resource Name----
-task 2
Any help would be greatly appreciated. My job is dependent on this.
Thanks in advance





RE: Custom View
View #1:
This can be achieved through the Resource Usage View
1. Click on >View, >Resource Usage
2. Insert the column called Project
3. Adjust your timescale accordingly
View #2:
This can be achieved through the Task Usage View
1. Click on >View, >Task Usage
2. Insert the column called Project
3. Adjust your timescale accordingly
4. You will then want to Group by Project - >Project, >Group by, >Customize Group by, >Project, OK
Hope this helps!
J Black
www.pmconnection.com