INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

negative point number

negative point number

negative point number

(OP)
When checking the reaction forces I found that there were a few points numbered as negative (like -100) by ETABS, and more wired was that I got force reported at these negative points, the total force including these negative points was balanced with applied loads. However, no such negative points were reported from building model! No coordinates were associated with these negative points so that I couldn't track down them. Anybody has this problem before? I had 3 different building models and  2 out of 3 have the negative point number problem. How can I get rid of this negative point numbering? Thanks

RE: negative point number

(OP)
ok, the problem is solved. the negative point numbering comes after the auto mesh of the wall as ETABS adds a restraint to the mid-node by default.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources