INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ICPR Ponds cascade through drops/pipe, steep

ICPR Ponds cascade through drops/pipe, steep

ICPR Ponds cascade through drops/pipe, steep

(OP)
Basically there are three ponds. Once the highest ponds reaches it's allowed stage it goes through a drop structure and down a pipe to the next and etc.   
I believe in error occurs in calculation once the pipe gets so steep.  If I have the pipe going at a small
slope it's causes pond staging lower than the greater slope I want to design.  For instance I'll increase the slope gradually and at 9% the ponds stage jumps ~6'! Thoughts?
Thanks.

RE: ICPR Ponds cascade through drops/pipe, steep

You may be getting the height of the hydraulic jump. Check to see what slope gives you critical flow.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources