Question about Sealing Dwgs
Question about Sealing Dwgs
(OP)
I do calcs for a manufacturing company and we let customers know what system or member size of our product are adequate. I'm an EIT, not a PE. I had a customer ask me to clarify something because the engineer sealing her drawings had questions. I answered the questions and fixed an error I found (minor, numbers were off but it didn't change the selection) and then read what the engineer wrote - he asked "Please send back additional info to confirm these sizes are satisfactory...once this (is) checked, (company) can sign and seal."
Shouldn't he be running the calcs himself if he intends to seal it, rather than relying on what I've sent to a customer? We make it clear on our end that we aren't PE's and that if they need sealed calcs, they should do that before ordering.
Thoughts?
Shouldn't he be running the calcs himself if he intends to seal it, rather than relying on what I've sent to a customer? We make it clear on our end that we aren't PE's and that if they need sealed calcs, they should do that before ordering.
Thoughts?





RE: Question about Sealing Dwgs
Sounds kind of like Simpson that sells wood connectors. They give the engineer all the tested values for their products. It is up to the EOR to use them correctly in his/her design. Simpson does not seal anything that I am aware of.
RE: Question about Sealing Dwgs
I've done work like that where the company I work for has taken the position that the specifications don't require the work to be sealed. I've nevered agreed with that position because I don't know how you establish that the work has been done by or under a P.E., unless the P.E. seals the drawings.
RE: Question about Sealing Dwgs
My understanding from the OP is that the EOR requested clarifications or revisions on a submission. The EOR then asked that the company sign and seal them. By that, I would assume he or she means the company you work for, or a PE hired by your company, is to sign and seal the design.
Information on what the spec requirements are may shed some light on the design responsibility.
RE: Question about Sealing Dwgs
Secondly, the issue of who stamps what can't be entirely fixed by agreement between the parties. Your state engineering rules come into play as well, and may require a PE for the application regardless of what your customers ask for or what you quote.
RE: Question about Sealing Dwgs
Dik