INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Weld repair 4340

Weld repair 4340

Weld repair 4340

(OP)
I'm trying to formulate a repair procedure for a part that has been EB welded. This isn't a weld integrity issue as much as it is cosmetic. Post machining of the weld area occasionally doesn't clean up the weld completely. I would like to fill in the pitts with a GTAW process and wonder about a preheat - postheat cycle to affect hydrogen embrittlement issues. Thanks for your time.

RE: Weld repair 4340

stillcrazy;
My expierence has been that filling in local pits or low spots with weld metal is difficult at best from a cosmetic standpoint because after welding, the surrounding area that was welded will pull in and create other low spots or crevices. One way around this problem is to first locally undercut the affected surface to allow for a weld build-up. The key after undercutting the surface is to raise the edge of the undercut region with a peening hammer or cold chisel to compensate for weld metal shrinkage. I would use the repair method below to weld build-up this undercut region with the GTAW process and ER80S-Ni2 filler metal.

The preheat should be 350 deg F and held for at minutes before welding. Use stringer beads with a 50% overlap to butter the area first, followed by a second weld pass while remaining on top of the first weld pass using a higher heat input (10-15%). After welding, allow the weld to sit at 500-550 deg F for 30 minutes. This should eliminate any delayed cracking issues.

The reason for the two passes is to use a technique known as temper bead to avoid post weld heat treatment of the base metal. I have used this technique on low alloy steels with success and with an experienced welder.

RE: Weld repair 4340

A procedure used sometimes while EB welding in vacuum, before repair is needed, is to preplace a titanium shim in the joint. It may help.

http://www.welding-advisers.com/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources