INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

NDT testing of new 8" gas pipe
2

NDT testing of new 8" gas pipe

NDT testing of new 8" gas pipe

(OP)
What are the ASME B31.3 NDT testing requirements for new above grade 8” diam. piping for gasoline in a terminal with a max. working pressure of 150 psi? The pipe has not been used. I am looking for guidance on how many of the welds should be X-rayed/mag particle tested and what is normally the spacing between UT locations.

RE: NDT testing of new 8" gas pipe

The minimum requirement is 5% RT. Refer to 341.4.1 of B31.3.

RE: NDT testing of new 8" gas pipe

(OP)
Thanks stanweld, I am out of town and do not have my B31.3. Does It give a minimum for the amount of UT that has to be performed as a baseline on the pipe and elbows?

RE: NDT testing of new 8" gas pipe

I/m not sure what you are asking. B31.3 does not require UT of pipe & fittings (base metals). The base materials specifications provide these requirements.

RE: NDT testing of new 8" gas pipe

(OP)
stanweld thanks and I am trying not to sound dumb, but I think I have passed that point. Should I be following API 570 for the UT information? I do have this guideline with me.  

RE: NDT testing of new 8" gas pipe

API 570 is used for inspection of pipe in service and for repairs. I assume that you wish to determine the original thickness of pipe/fittings installed. That's an Owner's decision. If you are not the Owner, it is not your concern unless specified in the Contract, in which case the locations and frequency of tests should be specified.

RE: NDT testing of new 8" gas pipe

(OP)
Thanks stanweld, you answered my questions. Have a good day.

RE: NDT testing of new 8" gas pipe

B31.3 is for newly constructed piping assemblies, it does not address corrosion monitoring guidelines. I think that is what you are talking about. Base lines for corrosion monitoring is up to the owner and should be specified. API 570 is the piping inspection code for inservice piping.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources