INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

stress relief a vessel

stress relief a vessel

stress relief a vessel

(OP)
if a P No.1 vessel is heat treated as a client requirement
(thikness 16 mm)
after that it was needed to fix a plate on the shell from OUTSIDE the, plate will be welded by fillet weld
will this impact the forgoing stress relieving process
and if we should re-PWHT,should this be applicable to wole vessel or just newly welded area of fillet weld

RE: stress relief a vessel

Yes, if the client requires it. Review ASME Section VIII, Div 1 UW-40, and UCS-56 for local PWHT guidance.

RE: stress relief a vessel

sometimes the user will forego the local PWHT if the additional weld is perfomed in accordance with UCS-56 with proper preheat and the weld size is small.

But since this is a client requirement, he will have to approve the procedure.  And the AI will have to approve welding after PWHT as well.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources