INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

vertical formwork striking

vertical formwork striking

vertical formwork striking

(OP)
Hi, looking into striking times of vertical formwork normally in water retaining applications. We typically use ggbs replacement mix. Apart from strength considerations what is minimum striking time used by others here? the ggbs will slow the strength gain and prolong the heat gain (although lower temps than non replacement mix). we have various 'guidance' here in UK and have advised site on times.

RE: vertical formwork striking

What is ggbs replacement mix?

RE: vertical formwork striking

(OP)
ggbs is ground granulated blast furnace slag. its a cement replacement material used for cost and also as stated to reduce temperature rises in section. also has enviromental advantages.

RE: vertical formwork striking

Formwork striking times - criteria, prediction and methods of assesment (R136)
Author(s): T A Harrison
Date: 1995
ISBN (13 digit): 978-0-86017-431-8
ISBN: 0-86017-431-X
Pages: 72
Publisher: CIRIA/Thomas Telford

RE: vertical formwork striking

Make sure you keep in mind what you are combining the GGBS with.  As an example, cements in Canada and US are different in chemistry.  US cements are low alkalis and Canadian cements are typically higher in alkalis.  The net effect, higher alkali cements activate slag better than lower alkali cements.  This will completely change the reaction rates.  Haven't read the book listed by Ussuri, but keep the location of cements in mind when comparing to your situation.

RE: vertical formwork striking

(OP)
hi thanks for the replies, I am quite happy with how I would specify types etc. but control of cracking is reliant heavily on standard of workmanship on site so was asking really for minimum striking times used by others. We have had a number of instances where site have requested absolute min. striking for programming and if possible would like to reduce our times further.

RE: vertical formwork striking

Is it worthwhile looking at concrete maturity monitoring?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.