pile's embedment depth din4014
pile's embedment depth din4014
(OP)
According to din 4014 the min pile's embedment depth in the bearing stratum is 2.5m.
So my question is: if the bearing stratum has an undrained strength cu=150 kN/m2 should the pile be embedded also 2.5 m or not? Note that the bearing layer extend to a large depth.
So my question is: if the bearing stratum has an undrained strength cu=150 kN/m2 should the pile be embedded also 2.5 m or not? Note that the bearing layer extend to a large depth.