Welding: LEAVE LOOSE condition at shipyards ??
Welding: LEAVE LOOSE condition at shipyards ??
(OP)
I have some structural drawings for a ship. I'm wondering what it means when the drawings indicate LEAVE LOOSE for the stiffeners on the bulkheads.





RE: Welding: LEAVE LOOSE condition at shipyards ??
RE: Welding: LEAVE LOOSE condition at shipyards ??
:)
OK, so then that portion left "loose" will be welded at a later time during the assembly process. Pls correct me if I am wrong.
Thanks alot.
RE: Welding: LEAVE LOOSE condition at shipyards ??