INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Warming up HP steam header

Warming up HP steam header

Warming up HP steam header

(OP)

We have a HP steam header through which 4 different plants (plus one Power plant)can either export or import HP steam.Many times when one or all plants r down, the header will be cold(Atmospheric condition).Before any plant can start using steam from power plant it has to be warmed up to a perticular temperature.Also for the purpose of venting steam(during warm up)we r  designing a Steam vent Silencer.
Header warm up rate is approximately 50 C per hour.

My question is How do I calculate steam flowrate necessary to get this warm up rate? I need this flowrate also to specify my steam vent silencer.

Thanks for any help  

RE: Warming up HP steam header

Why are you venting any amount of steam during warm-up? What is the operating pressure? Is the steam superheated?

Properly selected & installed steam traps will discharge any air present, and will pass the higher condensate load during the start up. Even if it is necessary to manually vent air, this will normally be done at very low pressures.

RE: Warming up HP steam header

I am with BigInch on this- you should be focused on draining the condensate (and venting noncondensibles). I can't believe that a warmup scenario could be related to a steam vent sizing basis.

There should be a warm up valve around the isolation valve for any section of the steam header which will be brought down. This warmup valve is typically 2" to avoid an unreasonable condensate slug which could cause a serious hammers if it can't be drained. The steam traps are typically bypassed straight to grade via oversized start-up drains. The purpose is to insure a well drained system. The main valve is not opened until the header is blowing steam out the trap bypasses. This is done after the trap bypasses are closed (sometimes these are closed in sequence as the header warms) and the normal traps are online. The header will come up to pressure. At that point the main block valve can be opened to put the header fully and safely on line. There is no "steam venting" in a normal sense.

50C/hr warm up rate seems an ambiguous basis for design as the header does not warm up uniformly. At fast warm-up rates (ie imaging just wheeling the steam wide open into a cold header) the hammer that can occur with a slug of condensate not well drained can be frightening- I have seen the aftermath of an 8" blind flange bursting off from exactly this sort of uncontrolled warmup, but fortunately no injuries.

best wishes,
sshep

RE: Warming up HP steam header

yikes, to top it off, temperature cycling is not a good thing either.

RE: Warming up HP steam header

Ya.  Start up of anything is the worst of everything all at the same time.  I'm always amazed at how many steady state designs you see out there where NOBODY ever thought about the start up scenario at all.  They just count on having 20% more power, 50% more transient pressure allowable and a field installed vent or drain at every high and low point.

http://virtualpipeline.spaces.msn.com

RE: Warming up HP steam header

cool,

It has been my experience that steam system components with "significant thicknesses" (such as steam drums, turbine casings etc.) or thick castings require a slow heat up time.

I have never heard of a slow heat-up time to protect relatively thin-walled steam piping (headers).

What is your header material, diameter and wall thickness ?

Are there thick steel castings ( i.e.e valve bodies) that are part of the system you are trying to protect ?

The comments and recommended actions mentioned above about valve bypasses and condensate drainage are valid and have been around for a long time, but thier purpose is to protect the system from waterhammer.

Have you seen Wayne Kirsner's superb and informative website ?

http://www.kirsner.org/pages/articlesAlt.html

More information please...

-MJC

  

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources