INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

MS Project Timescale

MS Project Timescale

MS Project Timescale

(OP)
Is there any way to change the timescale for a chart down to minutes or even seconds?

RE: MS Project Timescale

Right click on the time scale when you are in Gantt chart view.  Click on timescale.

Select the tier you want.  click on the units drop down box, then select the unit you want: quarterly, monthly, weekly, hourly, minutes.

That should do it.

Thanks,

RE: MS Project Timescale

(OP)
Thanks.  So minutes is the lowest you can break the timescale down too, correct?

RE: MS Project Timescale

Minutes is the lowest you can go.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources