INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Building Length Limitation for Concrete Slab

Building Length Limitation for Concrete Slab

Building Length Limitation for Concrete Slab

(OP)
Hi:

I remember there is a maximum length for concrete slab without pour strips or expansion joints.  Can anyone tell me what is the length and which code section?

If I remember right, this length limitation is different for pour strips and expansion joints.  The requirements are also different from conventional RC slab to post-tensioned slab.

Thank you for your help.

Shp6

RE: Building Length Limitation for Concrete Slab

Is this a slab on grade or structural floor slab above grade?

RE: Building Length Limitation for Concrete Slab

(OP)
This is an elevated slab.  

Does it make any difference if they are a residential building, office, or parking garage?

RE: Building Length Limitation for Concrete Slab

I don't think this is a code issue.  No cookbook approach applies.  Most large structural firms have their own technical guidance notes about spacing of the various types of joints in different types of structures, and these documents themselves are many pages long.  So your question is too complex to answer here.  It just depends on so many variables that each building requires its own assessment.  

RE: Building Length Limitation for Concrete Slab

For concrete frame buildings we used to use a max length of 50m for a full movement joint in the frame. Then you also have to look at the shrinkage effect on frame moments. If it's a braced frame you have to be more careful about where the braced bays are too.

Carl Bauer
www.bauerconsultbotswana.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources