INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

rubble foundation

rubble foundation

rubble foundation

(OP)
Have a project where the architect wants to remodel facade of building with 4" blocks.  Problem is the foundation wall consists of 3 different materials... stone, brick and concrete block.  In addition the brick slopes at the base approximately 15 degrees.  Anybody have any suggestions?  Height of the block is approximately 9 feet.


Thanks

RE: rubble foundation

The existing is battered stone?  And he wants to replace the battered stone into battered brick instead?

RE: rubble foundation

(OP)
no, the stone is currently parged.  He wants to attach a lintel to support the block which will be the new facade over the existing.

RE: rubble foundation

use very long thru bolts with epoxy?  Be very conservative maybe with the # maybe?  Or create a new foundation (hopefully your frost depth isnt very deep) and rest the facade on the new foundation.

RE: rubble foundation

(OP)
Thought about the foundation but I would need approximately 4 feet deep and would need to remove existing sidewalk.  The wall would probably be encroaching within the city's right of way which again would be a problem. I was actually thinking about installing HSS columns along the inside face and extending HSS stubs through the wall and welding my angle; again pretty expensive.

RE: rubble foundation

When adding a new facade of a heavy material such as block, normal practice is to remove the existing facade first.  Only if you are using a lightweight facade material such as aluminium panels should you consider leaving the existing heavy facade in place.  And the architect should know better.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources