INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

wireways

wireways

wireways

(OP)
Electrical mounting specifics needed

we are removing an old (1987)westinghouse VSD and replacing it with an A-B VSD, much smaller.

I want to mount some kind of wireway just above the floor where the conduits stup up thru the floor in the control room.

Mount the new boxes on the wall where the large ones were.

Looking for expert advice on the wireway and conduits to the new VSDPURGE

RE: wireways

OK, I'm wondering what you might mean by "expert advice".  I think you'll want to have a 10"x10" piece of "wireway"  a.k.a. "trough" or "auxiliary gutter" mounted on the wall, up a few inches off the floor (high enough for the conduits to be straight and connectors accessible for tightening).   A 10x10 trough should be large enough for wire bending and room to splice if so desired.

Bring the feed (line) into the drive in it's own metallic conduit(s) (HWG, GRC, EMT, IMC, it should be ferrous material as opposed to Aluminum), and the load conductors in their own conduit(s).  Leave adequate space around the VFD for cooling, and layout the wall space so that you could add a transformer or reactor later if you find you need one.  

Be sure to use grounding bushings on all the conduits, and a bonding jumper to the wireway, would probably be good too, although good assembly practices and use of "star" washers with fasteners and coppercoat or penetrox to keep good ground continuity throughout all enclosures and raceways is really how the work needs to be executed.

A-B has literature with extensive directions pertaining to the installation and wiring of VFDs.  Actually all VFD manufacturers have that kind of stuff, some better than ABs.

Hope this has been a little help.

Please let us all know how this works out for you! and don't forget FAQ731-376: Eng-Tips.com Forum Policies

RE: wireways

(OP)
It has been a long time since i have had to specify the details of installation in a scope of work.  Now just getting all the parts and pieces specified for a bill of material.

thank you for the tips

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources