INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Resource Graph Questions

Resource Graph Questions

Resource Graph Questions

(OP)
Hi everyone.
I've got a master project composed of several inserted projects.  I am trying to print a resource graph, but:
1) the resource graph shows duplicates of resources (that are only used in one project!)
&
2) it is showing resources over allocated when they are not even 100% allocated in the schedule.
Any ideas?

RE: Resource Graph Questions

The reason I can see a resource being over allocated is beacuse you have them assigned to do work at the same period of time.  You might want to check your resource pool to see if you have other projects associated with that person at the same time.  If you had created a project and delete that project that resource time will still be associated with the deleted project.  Make sure you unlink an deleted projects.

Check your task hours.  You might need to allocate more hours to your task.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources