Isolated phase busducts maintenance
Isolated phase busducts maintenance
(OP)
Dear all. On site, a CCPP 400MW nominal output and IPB manufactured by EGE. We are in the process of making maintenance contract with a contractor. I know tht somethings to be done is leak test with pressurized air, insulation test, inspection of bars, paint checks tightness of bolts, and so on. DO you know any company near Greece or in Europe general to provide such services?






RE: Isolated phase busducts maintenance
http://www.gordonkitto.co.uk/
----------------------------------
Sometimes I wake up Grumpy.
Other times I just let her sleep!
RE: Isolated phase busducts maintenance
Check tightness of connections
Check insulators
make insulation test
make air leakage test
Check for any ingress of dust or dirt
RE: Isolated phase busducts maintenance
=====================================
Eng-tips forums: The best place on the web for engineering discussions.
RE: Isolated phase busducts maintenance
My $0.02.
RE: Isolated phase busducts maintenance
RE: Isolated phase busducts maintenance
----------------------------------
If we learn from our mistakes I'm getting a great education!
RE: Isolated phase busducts maintenance
RE: Isolated phase busducts maintenance
----------------------------------
If we learn from our mistakes I'm getting a great education!