INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Requirements for engineers
4

Requirements for engineers

Requirements for engineers

(OP)
What are the requirements for engineers to make an approved pressure vessel design in the US?   Is a PE and knowledge of the particular ASME codes enough, or are there other certifications required?  Are the designs PE stamped?

RE: Requirements for engineers

Div. 1 calcs have no requirement for PE stamp

Div. 2 calcs and reports are PE stamped

RE: Requirements for engineers

dang, there is not edit button.

I should have said....some states may require PE stamp on calculations, but ASME does not require it

RE: Requirements for engineers

Requirements are primarily governed by the States or other local jurisdictions. Some require sign-off of Div. 1 vessels by a P.E. licenced in that State.

RE: Requirements for engineers

rlee53...

Requirements to "make"..??

By "make" the ASME Boiler & Pressure vessel code includes specify, design, fabricate, inspect and test.

Once you have done all of these things, in accordance with pre-approved proceedures and qualified welders with ASME approved and certified materials.....then and only then can you "certify" and register the vessel with an ASME Code Stamp.

Only certain metal fabrication shops are permitted by ASME to issue such certification.

No, a PE approval is not required for each and every calculation and drawing generation. But a PE approval is required for ASME VII Division 2 vessel calculations.

By the way, a vessel that is already fabricated cannot be "made into" an ASME vessel by any process of inspection or back calculation.

My opinion, recollection only.....

-MJC

  

RE: Requirements for engineers

(OP)
What part would a fabrication shop that already has an ASME "U" certificate outsource to a PE?

Would it  just be the "specify and design", or is there more? In other words, what would be the deliverables from the PE such as drawings, calculations, etc.?

RE: Requirements for engineers

lee,
The PE is required to certify a particular pressure vessel design (calculations in accordance with the code requirements, selection of materials, fabrication procedures, post weld heat treatment and more) is strictly in accordance with the design code requirements. Vessels designed to ASME VIII Div. 1 do not require PE certification, however, design per Div. 2 and 3 require PE certification, in addition to the U2 or U3 stamp aquired by the fabricator. Again, the PE is reviewing only the submitted documentation and if satisfied, he will stamp, sign and date the certified documents. He does not produce any calculation or any other deliverable to the fabricator, apart of his stamp, date and signature.
gr2vessels

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources