INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Multiple Battery Charger Demand

Multiple Battery Charger Demand

Multiple Battery Charger Demand

(OP)
Anyone know what sort of demand factor could be applied to the AC input load of multiple battery chargers for golf carts? This involves over 50 carts.  I'm assuming the chargers are integral with the carts but not being a golfer I don't know if this is true. Not that it would matter.

RE: Multiple Battery Charger Demand

At the end of a busy day, all the carts may be returned to the charging area and all put on charge simultaneously.
The demand factor will be 100% UNLESS you have specific information otherwise.
Bear in mind the consequences of a "loss of revenue event" due to not enough carts being ready when needed due to an inappropriate demand factor.
respectfully

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources