×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

cutting an area out of tunnel floor

cutting an area out of tunnel floor

cutting an area out of tunnel floor

(OP)
I have a large tunnel that I need to put a spread footing in.  The tunnel is 100 years old and the existing floor cannot support the load new column load.  I am proposing cutting a section of the floor out to install a new spread footing.  

The box section that represents the tunnel obviously has compressive forces acting through the floor ....I am thinking/hoping that those forces redistribute around the new opening and the floor handles those forces like a diaphram.....what kinds of things can I check to make sure this works as planed

RE: cutting an area out of tunnel floor

Sounds like a recipe for trouble. Perhaps you can avoid having to cut a large hole and possibly creating a big problem. Maybe several spaced smaller holes with micropiles installed thru each...

www.SlideRuleEra.net idea

RE: cutting an area out of tunnel floor

Design and install a moment frame by installing piece by piece with minimal disturbance and in-plane with the floor slab so as to take the loads.  Then remove the enclosed floor slab.  Perhap some studs on the frame at the cold joints.  Some field welding will be required for the moment connections.

VOD

RE: cutting an area out of tunnel floor

If the floor is just carring compression loads between the bases of the walls of the tunnels, Is it possible to use shoring to transfer the the thrust at the bottom of one wall to the bottom of the other wall. Much like trench shoring boxes transfer from one side to the other.

I can picture a beam along, and parrellel to, the base of each wall of the tunnel with a compression member at each end. The whole thing lying in a horizontal plane at the base of the wall.

Then cut out the floor between the compression memebers, place the new footings and columns, and repour the floor back in place.  

Just a thought.

RE: cutting an area out of tunnel floor

One more thing, you will have to confirm if this is possible by checking if the modified box section has capacity throughout and if the resulting bearing pressures are acceptable with the reduced bearing area.

VOD

RE: cutting an area out of tunnel floor

(OP)
the hole will be 20 feet or so from both tunnel walls.  wouldn't the slab (3' thick) act sort of like a 20' deep beam spanning across the length of the excavation?  the slab has reinforcement in both directions.....it seems like that slab would have to bend transversly to cause a problem...

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources