×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Splay rod install on pre-eng building

Splay rod install on pre-eng building

Splay rod install on pre-eng building

(OP)
I have a pre-engineered steel building 100'x50' and i have done a fast foundation design for it.  However i'm not sure if the building requires splay rods or not.  I have design the columns to sit on concrete piers and the piers are tied into the surrounding foundation wall.  Does anybody know where to get info on the design of splay rods?

RE: Splay rod install on pre-eng building

I am not familiar with the term "splay rods".  

Are you talking about embedded hairpins in the slab to take the lateral kick of the mainframes?

Mike McCann
McCann Engineering

RE: Splay rod install on pre-eng building

The hardest part of a pre-engineered building is handling the thrust loads to the foundations. Do you have the loads from the PEB manufacturer?

RE: Splay rod install on pre-eng building

If you are talking about thrust and hairpins, we have done some research on the matter.  We try to use hairpins where we can to carry the thrust into the SOG.  Our biggest question became when to use cross-ties from column to column.  It seems there is a point (at some thrust magnitudes) where your force resisting elements become riddled with assumptions concerning friction, transfer across construction joints...etc.  I would say that if you are in doubt and it is a rush job, do a thickened slab from column to column and embed cross ties.  

During our search we learned about a book that Butler Manufacturing published in the mid 80s.  It was a design guide on pre-engineered building foundations.  It contained some test data and good 'rules of thumb'...so I am told.  It is out of print for liability reasons.

If you find it let me know where to get it!

I would say that if you are in doubt and it is a rush job, do a thickened slab from column to column and embed cross ties.  Then there is no question.

cldea8

RE: Splay rod install on pre-eng building

If you have to do cross ties, I do not do a thickened slab, but a separate grade beam under the slab so there is no worry of construction joints and expansion/contraction. It is a separate pour, and there is some eccentricity, but this can be easily controlled.  Generally, with normal wind loads and reasonable eave heights, for mainframes 50' or less, single or double hairpins will work.  More load and larger spans- go to tension ties in a grade beam.  Whatever works.

Still do not know what he meant by "splay rods" though.

Mike McCann
McCann Engineering

RE: Splay rod install on pre-eng building

(OP)
Thankyou for your help, Splay rods is apparently just another name for hairpins.

RE: Splay rod install on pre-eng building

cldea8

I have a copy of the Butler Manufacturing Foundation Design and Construction Manual, although I have no idea how to get it out there for you. Any ideas?

RE: Splay rod install on pre-eng building

Really?  I am sure it is something you have had for quite a while and you wouldn't know where to purchase it?  Does it contain the 'rules of thumb' I read about online?

It is good to know it does exist anyway...

RE: Splay rod install on pre-eng building

It has a lot of good examples with design capacities. It is 176 pages long not including the appendix. Although I think most of the information you could get out of a good foundation design text with the exception of section that deals with foundations to resist horizontal forces. There is a lot of information in that section that I have not found elsewhere. I have the second edition, I don’t know if there are any editions released after.

RE: Splay rod install on pre-eng building

I have been designing pre-engineered buildings for a long time, and initialy found it very hard to find text related to the design of foundations of such buildings, because in all the concrete design books not much reference was available for foundations with high slip, and uplifting overturning moment.

Hair pin rebars uses the principle as tie rods, and in this system hairpin relies on the floor slab to function as the tie. Concrete itself cannot take much tension but the steel reinforcement within slab would. By lap splicing the horizontal loads are transfered to the floor slab.

to design a hairpin, divide the horizontal column reaction by an allowable tensile stress of the reinforcement (24 for Grade 60 steel, ) and you will get the area of steel to be used. The length of bar depends on the slab area to be engaged, it should be long enough for the assumed failure plane to intersect the desired number of slab rebar and to allow for their proper development.

Do keep in mind that for these hairpins your flooring should be reinforced. and not PCC. it would be a Slab on grade.

hope this helps

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources