Smart questions
Smart answers
Smart people
Join Eng-Tips Forums
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Member Login




Remember Me
Forgot Password?
Join Us!

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips now!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

Join Eng-Tips
*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.
Jobs from Indeed

Link To This Forum!

Partner Button
Add Stickiness To Your Site By Linking To This Professionally Managed Technical Forum.
Just copy and paste the
code below into your site.

chogben (Mechanical) (OP)
21 Aug 07 16:37
Hello,

I am looking for references on the design of drop boxes.  Guide lines for diameter depth of pool and erosion issues.

Does anybody have any experience with drop boxes?
Backfill (Mining)
27 Oct 07 18:06
chogben,
It has been a bit since I dropped in to look through some of the queries.  Hope this still is timely.

1. What material are you dropping?  Ore, aggregate or binder (types, gradation), slurry (percent solids, grind), liquid?

2. What is your drop height and conduit size/shape?

Since you mention pool, I gather you are dealing with slurry and/or liquid.  Are you after stilling basin layouts and such or tails drop boxes?

There's a lot of mixed terminology these days, thus my questions.
chogben (Mechanical) (OP)
29 Oct 07 8:29
Hello Backfill,

The service is a tailings line from a molybdenum flotation circuit.

P80=275 micron
37% solids by weight
SGmixture = 1.37
SGsolids=2.6
2300 cu.m/h
approximately 33% fines
Carrier - water

The slurry is pumped from a pump box over a haul road to run along a flat pipe bed.  Once outside of the plant boundaries (elevation 1440 m) the pipe bed slopes down at approximately 1.6% for 500m then 3.5% for another 1000 m to an elevation of 1410m.

From this elevation the slope is 12% down to a starting 1340 m and the crest of the tailings dam where the line feeds a dewatering cyclone.  The crest of the dam will grow over time.

I am considering a series of boxes to dissipate excess head in the system.

The slurry would flow into the top of the box and then exit through a gravity pipe near the bottom of the box.

Chris
Backfill (Mining)
1 Nov 07 17:42
Chris,
Our background and experience with tails is primarily stability, hydrology, liner systems and subaerial deposition.  My observance has been that drop boxes generally are three to four pipe diameters, with the outlet two to three box diameters above the sill (floor) of the box. The pipe runs themselves should be designed to balance settling and wear. I have seen non-technical references to -1%, but it's wise to run the numbers based on existing or expected settling characteristics.

A good place to start might be at http://www.tailings.info, which is managed by the folks over at Leeds University.  A pertinent text they reference is:
Vick, S. G. (1990). Planning, design, and analysis of tailings dams. Vancouver, BiTech.ISBN: 0921095120.2nd Edition.xi, 369

I see that his work is a primary basis for an EPA document I have used in the past, in disciplines or areas I mentioned at the top of my reply.  On that note, I would encourage looking over the rest of his work.

Hope this helps.  Sorry my own data is anecdotal at best.

Cordially,


Ralph R. Sacrison
Sacrison Engineering
www.sacrison-engineering.com

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close