INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

collector elements in lateral system

collector elements in lateral system

collector elements in lateral system

(OP)
I have a steel framed building using moment and braced frames as the lateral system.  Wind is controlling the lateral design as the building is in Seismic Category A.  Some of my braced frames and moment frames are located in the center of the building.  Does this mean I need to provide beams on either sides of the lateral frames to act as collector elements, or is the metal deck enough of a diaphragm to act as a collector?  If I do need to provide beams, do they need to be along the entire length of the building, or just immediately adjacent to the lateral frame?  Also, do they need to have tension controlled connections to prevent slipping and "banging bolts?"  Any help would be much appreciated.  Thank you.

RE: collector elements in lateral system

The metal deck needs to transfer its forces to collector beams that then in turn transfer its axial load to the braced frame or moment frame. The question of how many beams need to be collectors is determined by how much force needs to be collected. Can you provide enough connections without overstressing your diaphragm?

For metal deck, I prefer to use the entire beam line to collect the bracing force. Keep in mind that the collector force is coming in at the top flange of the beam and will create an additional moment in the beam plus you will have the axial load plus to the gravity moments. Make sure you look at the pass thru (axial) forces at the ends of the beams. You will probably need heavier clip angles, shear tabs, etc.

For concrete deck, you may be able to collect the forces in just a few beams by adding headed studs.


Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources