INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Microsoft Project Vs Others

Microsoft Project Vs Others

Microsoft Project Vs Others

(OP)
Is it your view that microsoft Prject is limited as PM software, is their better stuff out there???

Your Views Please

Lets get this forum debating!!!

RGDS

AB

RE: Microsoft Project Vs Others

Hi, I have been using Primavera, but I would like to know if I can switch to microsoft project because of the high cost of primavera...

Are there many differences between the 2?

thanks,

Cesar Baquerizo
www.conbaquerizo.com
Guayaquil, Ecuador

RE: Microsoft Project Vs Others

I would prefer Primavera above Microsoft project if you have the option. Far better control and scheduling options.
Your question if you can use MSP depends on the type of project . MSP2000 can work fine if you don't want any complex histograms / s-curves or early and late start calculations on your network logic. MSP will give you basic options and has a major drawback that you can only make 1 relation between 2 activities. Therefore no combination of SS and FF activities are allowed (often used for longer / overlapping act.'s).
Maybe this helps you a bit in the choice.

RE: Microsoft Project Vs Others

so, it only uses Finish to star relationships? you can't use SS, FF, etc?

RE: Microsoft Project Vs Others

U can use the others too, but no more than 1 relation between 2 activities.
So the relation between act.A en act.B can be either one of FS,SS,FF,or SF but not SS and FF.
In a true forward&backward network analysis to determine Early and Late dates this would result in open ends on the activity , if only SS ( open finish ) or only FF (open start) was used. The combination of SS and FF ( possible in P3) will prevent this.

RE: Microsoft Project Vs Others

I would have to agree with Hanp regarding Primavera as a project management tool (not just planning), except that the cost is so much greater.
You could also look at Suretrak, the 'baby' version of Primavera, which hasn't the same extensive learning curve and gives lots of the Primavera benefits at similar price to MS Project.
Regards,
Rentaplan

RE: Microsoft Project Vs Others

what about the compatibility between primavera and msoffice? is there any possibility to create any reports in word or excel docs?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources