INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Looking for ideas on conversion of system

Looking for ideas on conversion of system

Looking for ideas on conversion of system

(OP)
My client has a facility where the water supply is from a nearby town. The water supply line is 250 mm concrete and is about 6 km from the dedicated in line booster pump which feeds from the town’s domestic supply system.

After the meter pit the line becomes a 150 mm plastic, which flows 400 m to a reservoir. From the reservoir the water is re-pressurized (and chlorine added) and fed into the facilities domestic supply system. The facility has about 600 people on site during operating hours and another 200-300 people live in the attached housing area.

The existing line will not provide enough pressure to maintain domestic flows, let alone any necessary fire flows. The pumphouse has in addition to its electric domestic pressure pumps, a diesel driven fire booster pump that will provide large volumes at high pressure. (About 2,000 USGPM at 75 psi)

We also have a dedicated firewater reservoir for the main industrial part of the facility. It consists of three large diesel driven pumps and has storage capacity of 3,500 cu m and output of around 10,000 USGMP. This water is fed through a separate high-pressure loop.

We do however want to get rid of the pumphouse and have a closed loop from the town water supply.

In order to do this I am considering a series of in-line booster pumps spaced along the supply line, and increasing the size of the feed from the meter pit to the tie in points on the facility’s domestic system. If I cannot get sufficient fire flows for the domestic system I would leave the existing pumphouse and reservoir as a domestic area fire reservoir and feed it through the existing domestic system. (Simply super chlorinate the storage water and wait for a fire when the low pressure in the line would trigger start up of the booster pump.)

Does anyone have any experience in this type of conversion or any other ideas?

Thanks in advance

Rick Kitson MBA P.Eng

Construction Project Management
From conception to completion
www.kitsonengineering.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources