×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Mud Slab Over Top of Drilled Pier

Mud Slab Over Top of Drilled Pier

Mud Slab Over Top of Drilled Pier

(OP)
I am working on a project where concrete walls will span between drilled piers.  Will not have grade beams, maybe just a mud slab to set wall forms on.  There are fairly heavily loaded pilasters at the piers, supporting concrete columns above.  Contractor says for this condition they like to hold the pier down a few inches and run the mud slab over the top of the pier, in order to have a more finished surface to set the forms on, since top of drilled piers are typically very rough.  Has anyone seen this done before and/or have any precautions?

RE: Mud Slab Over Top of Drilled Pier

Are the walls precast? If so you will have eccentric loads on the piers when there is wall on only 1 side.

Also check that the corner is not going to break off.

csd

RE: Mud Slab Over Top of Drilled Pier

So are your column and wall connections interupted by the mud slab if you run the slab over the top of the pier?  Can the mud slab transfer the forces from the members into the piers in this case?  I'd guess no.

RE: Mud Slab Over Top of Drilled Pier

(OP)
Walls are c.i.p.  The mud slab would need to have strength adequate to transfer compression from pilaster to pier.

RE: Mud Slab Over Top of Drilled Pier

Sounds like you have a thinking contractor.  There is nothing wrong with his approach as long as the concrete in the "mud slab" will transfer the load from the walls and pilasters to the pier, and the reinforcement laps occur above the "mud slab".  Need to consider also any lateral loads you have.

RE: Mud Slab Over Top of Drilled Pier

Is the "mud slab" blinding concrete with a low compressive strength? in this case it cannot usually be used in place of structural concrete.

I assume the "drilled piers" are what I would call bored piles. Aren't they constructed using either bentonite or polymer excavation support? If this is the case they need to be cast high and then trimmed to the correct level.

Otherwise why not just cast to the correct level and then spend some time getting a good enough surface to set the forms on.

RE: Mud Slab Over Top of Drilled Pier

(OP)
The piers are 4' to 6' diameter.

RE: Mud Slab Over Top of Drilled Pier

The contractor is trying to save the cost of extra formwork at the caisson. I would have him stop the mudslab short of the caisson and provide the extra formwork and waler at the bottom across the width of the caisson.

RE: Mud Slab Over Top of Drilled Pier

jike, didn't understand that.

Is my decription correct. The drilled piers (4' to 6'in diameter)will have cast in-situ walls between them. Directly above them the piers will have a rectangular column, which is in effect a thickening of the wall (a pilaster)

The pilaster will need formwork, the contractor intends to cast bliding concrete (mud slab) on which all this formwork will sit.

What we don't know is the dimension of the pilaster compared to the drilled pier. Assuming the pilaster is larger than the drilled pier the mud slab can surround the pier but not run over the top of it.

If the pilaster is of smaller dimension than the pier and the forms somehow have to sit on the pier then structural concrete wll have to be used.

RE: Mud Slab Over Top of Drilled Pier

The formwork for the walls and pilaster is essentially all part of the same except the pilaster is bumped out on one or both sides. I am assuming that the bottom of the mudslab is even with the top of the caisson then the top of the mud slab is higher and does not extend over it, then there will be a some area below the form that needs to be fill in with more formwork.

RE: Mud Slab Over Top of Drilled Pier

(OP)
The overall footprint of the pilaster (including wall thickness) is 20" x 36", which is smaller than the minimum drilled pier size (48") we will be using.

RE: Mud Slab Over Top of Drilled Pier

jike,

You didn't read the OP properly.  The contractor wants to run the "mud slab" through over the piers to simplify his formwork.  Nothing wrong with that, in fact it shows good common sense. Mrengineer has stated that the "mud slab" concrete has to be strong enough to transfer the pilaster load.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources