Commissioning of Condensing Steam Turbine Generator
Commissioning of Condensing Steam Turbine Generator
(OP)
Hi,
We are going to commission a 25MW condensing STG soon. Any experience to share
ppm
We are going to commission a 25MW condensing STG soon. Any experience to share
ppm





RE: Commissioning of Condensing Steam Turbine Generator
Back up lube oil,
Emergancy governor,
Casing drains
Primary speed control and
Push button trip are operational.
On the generator side;
voltage regulator and
breaker phasing