INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Concrete Slab-On-Grade Control Joint Reinforcement

Concrete Slab-On-Grade Control Joint Reinforcement

Concrete Slab-On-Grade Control Joint Reinforcement

(OP)
I have always detailed my control joints for a slab-on-grade with the reinforcement running continuous through the joint.  I show a (1/4)*slab thickness cut and the steel mesh or other reinforcement running continuous.  Does anyone terminate there reinforcement at the joint?  Why?

RE: Concrete Slab-On-Grade Control Joint Reinforcement

I don't detail it.  I just put a note on the plan.  I would put it continuous, if it is not, I wouldn't worry about it.  It is only slab on grade after all.

http://www.swijetty.com
Sea Water Intake and Jetty Construction

RE: Concrete Slab-On-Grade Control Joint Reinforcement

For run of the mill thin slabs, I have usually specified that alternate wires are cut at sawn joints.  Just go through with bolt cutters and nip out a 4' section of every other wire.  And if they saw the joint at the same place, I think it goes some way toward making the crack occur where it is intended.

RE: Concrete Slab-On-Grade Control Joint Reinforcement

I detail saw joints to have 1/3 of the reinforcing (rebar not wire mesh) continuous thru the joint.  The other bars stop 3" each side of the joint.  The purpose of the joint is to create a weakened vertical plane in the slab to cause the slab to crack at that location.  If the bars are continuous thru the joint, there is no weakened plane because the rebar holds everything together.  It doesn't really matter as far as the servicability of the slab.  But having cracks occur in a joint looks better aesthetically than cracks at random locations in the slab.  Having 1/3 of the bars continuous thru the saw joint allows the slab to crack in the joint, but helps prevent the slab from settling differentially on each side of the joint.  I've used this successfully many times over the years.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources