Resource "re-leveling" question
Resource "re-leveling" question
(OP)
Has anyone seen the problem of trying to relevel if future task is completed? MS Project will not remove completed tasks from the resource's future workplan.
For example:
Assume all of the following tasks are performed by the same resource.
Task 1: July 1 - July 8
Task 2: July 9 - July 16
Task 3: July 17 - July 24
Task 4: July 25 - July 31
If task 3 gets completed, I do not see Task 4 get moved up a week when I re-level. MS Project will not move Task 4 into that week. Am I missing an option on a submenu somewhere?
For example:
Assume all of the following tasks are performed by the same resource.
Task 1: July 1 - July 8
Task 2: July 9 - July 16
Task 3: July 17 - July 24
Task 4: July 25 - July 31
If task 3 gets completed, I do not see Task 4 get moved up a week when I re-level. MS Project will not move Task 4 into that week. Am I missing an option on a submenu somewhere?





RE: Resource "re-leveling" question
The project manager "manages" his project. So if a task 3 weeks hence gets completed early, then he should re-arrange his project to reflect this.
TygerDawg
Blue Technik LLC
Advanced Robotics & Automation Engineering
www.bluetechnik.com
RE: Resource "re-leveling" question
Specifically, the early finish date must reflect the fact that the task was finished at a date earlier than scheduled, otherwise, the program simple assumes that the task is complete on the schedule as implemented, hence, no compression of time for the remaining tasks.
TTFN
FAQ731-376: Eng-Tips.com Forum Policies