Timber floor on top of concrete screed
Timber floor on top of concrete screed
(OP)
Hi lads. If anyone could give me an answer how to get moisture out of the concrete floor 120-150 mm thick to the level of 0,6-1,6% so that i could put timber floor on it, two weeks after it's been poured?
I know that it sounds pretty extreme because you need about 6 months for the concrete to complete dry out.
P.S. Strength of concrete is around 50N/mm2 after 28 days.
I know that it sounds pretty extreme because you need about 6 months for the concrete to complete dry out.
P.S. Strength of concrete is around 50N/mm2 after 28 days.





RE: Timber floor on top of concrete screed